Oklahoma Mechanics Lien Deadlines

If you're a sub or supplier on a home where the owner lives, your lien is void unless you send a pre-lien notice within 75 days of your last day on the job, whatever the amount.

Plain-language rules for general contractors, subcontractors and suppliers on private jobs, from Title 42 of the Oklahoma Statutes, plus a helper that works out your dates.

Oklahoma Deadline Helper

Answer a few questions about the job and get your dates, with calendar reminders. Nothing you enter leaves your browser.

Your best guess is fine; update it when you finish.

This is general information, not legal advice. Lien deadlines are strict and can change with details of your job that this tool doesn't ask about. Our recommended dates are set earlier than the legal deadline on purpose. If money is on the line, talk to a construction attorney in your state before your deadline.

Enter your first and last day on the job to see your dates.

Oklahoma at a glance

General contractorSub or supplier
Notice during the jobNonePre-lien notice within 75 days after last work (owner-occupied home: always; other jobs: if claim is $10,000+)
File the lien4 months after last work90 days after last work
Sue to enforce1 year after filing1 year after filing

If you're a subcontractor or supplier

  1. Send a pre-lien notice to the property owner and the general contractor no later than 75 days after your last day of work, and before you file a lien. On a home where an owner lives, it's required for any amount. On other jobs it's required when your claim is $10,000 or more. It isn't required on a 1 to 4 unit home where no owner lives. One notice covers the whole project. Send it by certified mail with return receipt (it counts the day you mail it) and keep the receipt. Miss it and the part of your lien it should have covered is invalid. (42 O.S. § 142.6)
  2. File your lien statement with the county clerk in the county where the property is, within 90 days after your last day of work. It must be verified (notarized), and you hand the clerk a notarized affidavit that you sent the pre-lien notice. (42 O.S. §§ 143, 142.6(C))
  3. Sue to enforce within 1 year after you file, or the lien is lost. (42 O.S. § 172)

If you're the general contractor

  1. No pre-lien notice is required of you. It only applies to people who did not contract directly with the owner. (42 O.S. § 142.6(A))
  2. File your lien statement with the county clerk within 4 months after your last day of work. Give the clerk the owner's mailing address; the clerk mails the owner a notice of the lien. (42 O.S. §§ 142, 143.1)
  3. Sue to enforce within 1 year after you file. (42 O.S. § 172)

Watch out for

How we count: Oklahoma's lien law has no rule that moves a deadline off a weekend or holiday, so we never assume one. Our recommended dates are 7 days before the legal deadline (30 days for the lawsuit), moved earlier to a weekday.

The law

Oklahoma's mechanics' and materialmen's lien rules are in Title 42, sections 141 to 154, of the Oklahoma Statutes. We read the official compilation, which includes the 2025 changes that took effect January 1, 2026 (those changed criminal penalties only, not deadlines).

More from Trade Bid Tools

Trade Bid Tools is not a law firm, and this page is not legal advice. We summarize state statutes in plain language and link to the official text; the statute controls if anything here differs. Laws change, and courts read them in ways a summary can't capture. Rules last checked against the statute on October 16, 2026. Using this page doesn't create an attorney-client relationship. Found something out of date? Tell us.